Auvers-sur-Oise, Notre-Dame-de-l'Assomption

AUVERS-O

Building Data for Auvers-sur-Oise, Notre-Dame-de-l'Assomption

  •  
  • Type: Abbey
  • Affiliation: Augustinian
  •  
  • Region: Ile-de-France
  • Department: Val-d'Oise
  • Coords: 49.071, 2.1761
  •  
  • Surveyed: 1977, 1980-83, 2003, 2014

Map

Click and drag to rotate; Roller to zoom; Arrow keys to pan

Virtual Tour

Timeline and building units for Auvers-sur-Oise, Notre-Dame-de-l'Assomption A 'building unit' is an arbitrary unit of work based on bulk billing techniques used by quantity surveyors. 
    	    The unit is small enough to provide realistic figures in the small churches without becoming too huge in the large. 
    	    Six units would pay for one small vaulted bay in an aisle about 3 metres square, or a small first-floor gallery. 
    	    Such a bay would consist of an external wall with a small window, half of two columns about 3 meters tall, the floor and footings under them and the vault and roof overhead.
X

A 'building unit' is an arbitrary unit of work based on bulk billing techniques used by quantity surveyors. The unit is small enough to provide realistic figures in the small churches without becoming too huge in the large. Six units would pay for one small vaulted bay in an aisle about 3 metres square, or a small first-floor gallery. Such a bay would consist of an external wall with a small window, half of two columns about 3 meters tall, the floor and footings under them and the vault and roof overhead.

info

gray gray 65
1090
gray 60
1110
90
1120
40
1130
gray 100
1180
65
1190
120
1200
56
1210
gray
1050 1090s 1110s 1120s 1130s 1180s 1190s 1200s 1210s 1250

Phases for Auvers-sur-Oise, Notre-Dame-de-l'Assomption The building sequence is based on my on-site analysis of the construction history,  
    	    using the techniques developed on the cathedral of Chartres called toichology, and described in a number of publications.
    	    The analysis of some of the smaller churches are more approximate than I would like, and need further analysis. 
    	    <p>I have used 'phase' rather than 'campaign' to to identify a contiguous zone with similar elements. 
    	    A campaign would be defined by recognisable breaks and construction joints in the fabric: there may be a number of phases within a campaign.
    	    One benefit is that separate programs by subcontractors, such as carvers, may be isolated, which is particularly useful in complex sections, such as portals.
    	    <p>Every phase has been assigned to a decade, so there may be more than one phase in a decade. 
    	    <p>While this is certainly imperfect, it will allow us to explore all the data, including costs, across time. 
    	    This is an on-going process, so as the data continues to be analyzed, the chronology and costing analysis will be further refined, and the synopsis updated. 
    	    <p>Clicking on any of the decade graphics will display all buildings that had work being done during that decade.
X

The building sequence is based on my on-site analysis of the construction history, using the techniques developed on the cathedral of Chartres called toichology, and described in a number of publications. The analysis of some of the smaller churches are more approximate than I would like, and need further analysis.

I have used 'phase' rather than 'campaign' to to identify a contiguous zone with similar elements. A campaign would be defined by recognisable breaks and construction joints in the fabric: there may be a number of phases within a campaign. One benefit is that separate programs by subcontractors, such as carvers, may be isolated, which is particularly useful in complex sections, such as portals.

Every phase has been assigned to a decade, so there may be more than one phase in a decade.

While this is certainly imperfect, it will allow us to explore all the data, including costs, across time. This is an on-going process, so as the data continues to be analyzed, the chronology and costing analysis will be further refined, and the synopsis updated.

Clicking on any of the decade graphics will display all buildings that had work being done during that decade.

Short version of history

Earlier

Phase 1 - Earlier - transept (b)


West wall of north transept to height of 2&plusmn; metres; there are vertical joints in the nw2 corner and against the nave aisle wall that show this stretch of masonry was earlier; in the south transept the west wall may also have been from the same period, but it is not as clear; complex construction suggests the piers of an earlier choir were encased in present crossing piers; in a later campaign, 3 bays to nave aisle walls with rectangular pilasters to sills with vertical joints against the transept walls and at the western end against the w4 aisle shafts; no indication of date; the evidence for this being the earliest comes from the complex stonework at the entry into the north aisle;
Earlier

Phase 2 - Earlier - transept nw


In the wn1 corner the wn1 crossing pier was built many years after the west side of the transept wall and the northern nave wall; it has a projection into the aisle that matches the earlier transept wall; the arch that was constructed between them may have seemed too narrow to secure the weight of the intended crossing tower, for a second arch was laid over it, and is supported on the crossing pier and on a projecting pilaster added to the nave aisle wall; this second arch is off-centre to the lower arch, which would have caused difficulties in erection; to resolve this the upper part of the nave wall was enlarged with a pilaster to support the upper arch over the entry; the underside of the projection is a well-carved convex moulding in which nothing has been chopped back or added in, but every stone was carved to fit and erected in sequence at the time that the projection was built; the projection included the shafts for the future nave aisle vault, which dates it to the time the same decision was taken in the crossing pier; the underside of the pilaster is level with the sill of the adjacent window that seems to mark the moment when the older nave wall was raised to its present height;
1090

Phase 3 - 1090 [1092] - transept 10c - 15 Units


North and east walls of north transept probably with the chapel and the external walls of the apse up to course 10, about level with the top of the pre-existing west transept wall; the apse has central buttresses and the polygonal walls are at 80 degrees to one another, suggesting an unusual geometry; at this level the masonry between the chapel and the apse is continuous, and the plinth was laid at exactly the same height, though repairs in the corner leave a little ambiguity; only 8 courses in the south transept noted where the width of the corner buttress was reduced;
1090

Phase 4 - 1090 [1093] - transept 8c - 10 Units


Continued with the walls of the north transept and chapel for 8 courses to the window sills; joint indicated by setback to exterior face of the north wall by ne2 buttress; this includes the start of the wide windows; the south transept probably follows su
1090

Phase 5 - 1090 [1094] - n chapel (aw) - 15 Units


The chapel window capitals and arch, but the groin vault was not part of this campaign; north transept continued along the north wall and with a few courses over the older aisle wall to the west;
1090

Phase 6 - 1090 [1095] - chapel (rc) - 25 Units


North chapel coping, possibly with a timber roof; the coursing continued to the side of the adjacent (now blocked) window, and to the underside of the north-n window sill; the north terminal wall was thinned just below the sill, marking the end of this campaign just below the corbels for the ribs; massive bases for the western crossing piers with 8 courses; the shafts for the aisles and the projection to the west came later, with the joints in the nw corner and on the west side of the nave rib shaft; coursing shows the western leg of the north transept was built up to 4 courses above the narrow lower opening into the nave aisle, which therefore links the western crossing piers to the work in the transepts; the north leg of the crossing pier wn1 is 26mm wider than then the pilaster on the old transept wall on the opposite side, and the width of the lower arch matches the crossing pier and not the wall, confirming that crossing pier and arch were installed after the north wall; in the south began the large openings in lateral walls;
1110

Phase 7 - 1110 [1114] - east (a) - 30 Units


East end continued after crusade in at least 4 campaigns for ribs throughout; apse shaft bases added onto the inside faces of the walls, from misalignments with the exterior corners; en1 pier to different design and dimensions to those in the apse, and therefore in a different campaign, and in another the rib shafts on crossing side of w1 were added up to 8th course, and on north side a projection to support arch over entry into aisle, and with a shaft ready for rib vaults in the aisles; includes apse capitals
1110

Phase 8 - 1110 [1118] - east (a) 1 - 30 Units


Apse and sanctuary walls and vaults continued to capitals to eastern crossing piers and start of e2 doubleau; in north chapel replaced southern half of the entry arch to a different arc and pointed, during which the older pier was encased within a larger en1 crossing pier to support the intended tower; as the groin vault follows the outline of the pointed arch it was built then, while the stonework in the groins precludes the possibility that only a part of the vault had been demolished and rebuilt; thus the whole of the groin was built with the enlarged crossing pier; the coping and roof over the north chapel built as vault filled over;
1120

Phase 9 - 1120 [1126] - east (v) - 30 Units


Apse and e1 ribs, completed e1 doubleau; on north side of w1, the arch over the transept-to-aisle opening was strengthened to support a second arch to the same width as crossing pier;
1120

Phase 10 - 1120 [1126] - n nave 1(a) - 20 Units


West crossing aisle on north side to capitals; replaced but I have assumed close to originals. At least five campaigns. A piers. B west front with chunky griffes. C W.c arches and Arcade Arches. D simple ribs and boss. E more complex ribs and shafts over piers and complex boss Rib profile round 1-2, pointed 3-4. 1-2 is English style vault with dropped round ribs. Could these have been built in 50s and piers put under them later? Junctions determined mainly from profiles of stair treads. A to 12, B to 19 with W.c jamb. C two treads with caps to W1-3? and W.c arch. E to 24. F varied section to 30 without ribs and caps. G to triforium. Slit windows confirm this scenario. West wall with adjacent walls to last bay and dado arcades. B probably Bronze. Corbel, details = Chartres. C = Taverny K. Same caps in (t) and (c). Shafts over piers show same step between 2 and 3.
1120

Phase 11 - 1120 - nave 1 (av) - 20 Units


Nave aisles vaults in first bay north and south with flattened rib outline, in the English manner; this forced later aisle vaults to be squatter than usual.
1120

Phase 12 - 1120 [1126] - w crossing (c) - 20 Units


West crossing clerestory capitals and to the aisle with doubleau from crossing into north and south transept; the latter w1(a)w capitals are replacements, and if they were copies of the originals, have the same impost and decoration as clerestory capitals overhead; there is a clear joint where the shafts were reduced 1 course above the aisle caps, and with 12 courses from aisle impost to clerestory this section would have been the work of at least two campaigns; this argues that the aisle capitals wn1aisles w were inserted into the crossing pier at the same time as those in the clerestory; dates ex chars nave and chateau-landun;west crossing clerestory capitals and to the aisle with doubleau from crossing into north and south transept; the latter w1(a)w capitals are replacements, and if they were copies of the originals, have the same impost and decoration as clerestory capitals overhead; there is a clear joint where the shafts were reduced 1 course above the aisle caps, and with 12 courses from aisle impost to clerestory this section would have been the work of at least two campaigns; this argues that the aisle capitals wn1aisles w were inserted into the crossing pier at the same time as those in the clerestory; dates ex Chars nave and Chateau-Landun;
1130

Phase 13 - 1130 - upper transepts - 20 Units


Coursing connects the western crossing capitals to transept walls; n-n window begun, with corner shafts in the transepts on corbels to support a rib vault; wall taken to underside of oculus and continued to meet the wn1clerestory crossing caps; same in the south, though west wall steps up to crossing caps as south was still some courses below the north;
1130

Phase 14 - 1130 - transept (v) - 20 Units


Crossing and transept vaults, and room over crossing for tower, that shows intended lower roof over nave at same level as transepts;
1180

Phase 15 - 1180 - w4-5 dado - 20 Units


W4-5 bases and lower courses of portal and dado to tread 12; main evidence for nave campaigns lies within the west stairs, and confirmed in small changes elsewhere; probably removed west wall of old nave;
1180

Phase 16 - 1180 - portal caps - 20 Units


West bay to tread 19 with portal caps and arch, and dado arches to window sills;
1180

Phase 17 - 1180 - west (a) - 20 Units


West bay to tread 24 with sills, pier caps and vault, buttresses built with top two courses of aisle walls which are almost complete while the earlier nave remained untouched within them.
1180

Phase 18 - 1180 - drums w - 20 Units


Two western drum pier bases with large chunky griffes possibly built within the nave while it was still in use.
1180

Phase 19 - 1180 - drums e - 20 Units


Three eastern drum piers, arches and shafts; all drums have the same imposts; drum capitals, arches and shafts; last moment to remove old nave walls and roof.
1190

Phase 20 - 1190 - aisle (v) - 20 Units


Aisle window heads, roof and completion of aisle vaults; arcade to 3 courses below triforium string, located by changes from en delit shafts to engaged; flyers were intended;
1190

Phase 21 - 1190 - nave (t) 6c - 45 Units


Nave triforium of 6 courses using a finer stone to 2 courses above string; w1 shafts for clerestory shifted back and reduced in diameter; laid western internal walkway and started frame for west rose (replaced 1870s);
1200

Phase 22 - 1200 [1200] - nave (t) 8c - 40 Units


Nave triforium of 8 courses with en delit shafts, using same stone to top of 3-course tas-de-charge up to joint over clerestory external walkway;
1200

Phase 23 - 1200 - nave (c) - 40 Units


Nave clerestory window jambs and head; external walkway and piers for flyers; west rose;
1200

Phase 24 - 1200 - nave 1-2(v) - 40 Units


Nave high vaults in east two bays
1210

Phase 25 - 1210 - nave 3-4(v) - 25 Units


Nave vaults bays 3-4;
1210

Phase 26 - 1210 - s aisle wall - 6 Units


South nave wall; note that south portal and oculus were inserted at a later date.
1210

Phase 27 - 1210 - tower II - 25 Units


Tall tower upper stage in at least 3 campaigns;
Later

Phase 28 - Later


Install new pier in wn2, presumably removing part of earlier building; all apse windows have been replaced;